Financial statements for the 3rd QTR of 2023 DEWA
Document42 pages, a scan, read by AshumOpen DFM’s file
Page 1
Dubai Electricity and WaterAuthority (PJSC) andits subsidiaries
Condensed consolidated interim financial information
for the nine-month period ended 30 September 2023 (unaudited)
Page 2
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Condensed consolidated interim financial information for the nine-month period ended 30 September 2023 (unaudited)
Contents | Pages
| Independent auditors' report on review of condensed consolidated interim financial information | 1 - 2 |
|---|---|
| Condensed consolidated interim statement of financial position | 3 |
| Condensed consolidated interim statement of profit or loss and other comprehensive income | 4 |
| Condensed consolidated interim statement of changes in equity | 5 - 6 |
| Condensed consolidated interim statement of cash flows | 7 |
| Notes to the condensed consolidated interim financial information | 8 - 40 |
Page 3
KPMG Lower Gulf LimitedThe Offices 5 at One CentralLevel 4, Office No: 04.01Sheikh Zayed Road, P.O. Box 3800Dubai, United Arab EmiratesTel. +971 (4) 4030300, www.kpmg.com/ae
Independent Auditors' Report on Review of CondensedConsolidated Interim Financial Information
To the Shareholders of Dubai Electricity and Water Authority (PJSC)
Introduction
We have reviewed the accompanying 30 September 2023 condensed consolidated interim financial information of Dubai Electricity and Water Authority (PJSC) ("DEWA" or "the Authority" or "the Company") and its subsidiaries ("the Group"), which comprises:
• the condensed consolidated interim statement of financial position as at 30 September 2023;
• the condensed consolidated interim statements of profit or loss and other comprehensive income for the three-month and nine-month periods ended 30 September 2023;
• the condensed consolidated interim statement of changes in equity for the nine-month period ended 30 September 2023;
• the condensed consolidated interim statement of cash flows for the nine-month period ended 30 September 2023; and
• notes to the condensed consolidated interim financial information.
Management is responsible for the preparation and presentation of this condensed consolidated interim financial information in accordance with IAS 34, "Interim Financial Reporting". Our responsibility is to express a conclusion on this condensed consolidated interim financial information based on our review.
1
KPMG Lower Gulf Limited, licensed in the United Arab Emirates and a member firm of the KPMG global organization of independent member firms affiliated with KPMG International Limited, a private English company limited by guarantee All rights reserved KPMG Lower Gulf Limited (Dubai Branch) is registered and licensed under the laws of the United Arab Emirates
Page 4
Dubai Electricity and Water Authority (PJSC) Independent Auditors' Report on Review of
Condensed Consolidated Interim Financial Information30 September 2023
Scope of Review
We conducted our review in accordance with the International Standard on Review Engagements 2410, "Review of Interim Financial Information Performed by the Independent Auditor of the Entity". A review of condensed consolidated interim financial information consists of making inquiries, primarily of persons responsible for financial and accounting matters, and applying analytical and other review procedures. A review is substantially less in scope than an audit conducted in accordance with International Standards on Auditing and consequently does not enable us to obtain assurance that we would become aware of all significant matters that might be identified in an audit. Accordingly, we do not express an audit opinion.
Conclusion
Based on our review, nothing has come to our attention that causes us to believe that the accompanying 30 September 2023 condensed consolidated interim financial information is not prepared, in all material respects, in accordance with IAS 34, "Interim Financial Reporting".
KPMG Lower Gulf Limited
Emilio PeraRegistration No.: 1146Dubai, United Arab Emirates
Date: 10 NOV 2023
2
KPMG Lower Gulf Limited, licensed in the United Arab Emirates and a member firm of the KPMG global organization of independent member firms affiliated with KPMG International Limited a private English company limited by guarantee All rights reserved KPMG Lower Gulf Limited (Dubai Branch) is registered and licensed under the laws of the United Arab Emirates
Page 5
Dubai Electricity and Water Authority (PJSC) and its subsidiariesCondensed consolidated interim statement of financial position as at
| 30 September | 31 December | ||
|---|---|---|---|
| Notes | 2023 | 2022 | |
| AED'000 | AED'000 | ||
| (Unaudited) | (Audited) | ||
| Assets | |||
| Non-current assets | |||
| Property, plant and equipment | 6 | 154,919,653 | 154,029,411 |
| Intangible assets | 7 | 456,375 | 471,123 |
| Investments accounted for using the equity method | 8 | 640 | 640 |
| Derivative financial instruments | 9 | 2,008,797 | 1,294,802 |
| Financial assets at fair value through other comprehensive income | 10 | 54,310 | 52,911 |
| Investment property | 11 | 83,385 | 72,859 |
| Other assets | 12 | 996,600 | 1,134,897 |
| Other financial assets | 13 | 2,747,862 | 1,457,956 |
| Total non-current assets | 161,267,622 | 158,514,599 | |
| Current assets | |||
| Derivative financial instruments | 9 | 641,107 | 492,106 |
| Other assets | 12 | 507,538 | 131,845 |
| Other financial assets | 13 | 3,745,810 | 3,133,758 |
| Inventories | 14 | 1,414,521 | 1,445,216 |
| Trade receivables | 15 | 5,024,492 | 4,172,854 |
| Short-term deposits | 16 | 5,627,925 | 7,532,503 |
| Cash and cash equivalents | 17 | 5,270,958 | 5,287,415 |
| Total current assets | 22,232,351 | 22,195,697 | |
| Total assets | 183,499,973 | 180,710,296 | |
| Equity and liabilities | |||
| Equity | |||
| Share capital | 18 | 500,000 | 500,000 |
| Capital contribution | 18 | 40,042,885 | 40,042,885 |
| Statutory reserve | 18 | 591,346 | 591,346 |
| Hedging reserve | 18 | 1,401,479 | 954,247 |
| Retained earnings | 18 | 45,475,008 | 47,338,862 |
| Equity attributable to Owners of the Company | 88,010,718 | 89,427,340 | |
| Non-controlling interests | 3,904,404 | 2,953,130 | |
| Total equity | 91,915,122 | 92,380,470 | |
| Liabilities | |||
| Non-current liabilities | |||
| Derivative financial instruments | 9 | 808 | 4,578 |
| Borrowings | 19 | 29,587,665 | 37,317,975 |
| Retirement benefit obligations | 20 | 1,027,600 | 1,010,493 |
| Lease liabilities | 21 | 16,352 | 23,528 |
| Other long-term liabilities | 22 | 33,069,623 | 32,802,528 |
| Total non-current liabilities | 63,702,048 | 71,159,102 | |
| Current liabilities | |||
| Borrowings | 19 | 9,958,298 | 3,371,854 |
| Lease liabilities | 21 | 11,648 | 12,884 |
| Trade and other payables | 23 | 17,837,741 | 13,690,643 |
| Total current liabilities | 27,807,687 | 17,075,381 | |
| Total liabilities | 91,509,735 | 88,234,483 | |
| Total equity and liabilities | 183,424,857 | 180,614,953 | |
| Regulatory deferral account credit balance | 24 | 75,116 | 95,343 |
| Total equity, liabilities and regulatory deferral account credit balance | 183,499,973 | 180,710,296 |
To the best of our knowledge, the condensed consolidated interim financial information fairly represents in all material respects, the financial position, results of operation and cash flows for the Group as of and for the nine-month period ended 30 September 2023.
The condensed consolidated interim financial information was approved and signed on behalf of the Board of Directors on 10
November 2023 by;
Managing Director &Chief Executive Officer
Chairman
The independent auditors' report on review of condensed consolidated interim financial information is set out on pages 1 and 2.
The notes on pages 8 to 40 form an integral part of this condensed consolidated interim financial information. 3
Page 6
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Condensed consolidated interim statement of profit or loss and other comprehensive income
| For the nine-month period ended 30 September | For the three-month period ended 30 September | ||||
|---|---|---|---|---|---|
| Notes | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | |
| Revenue | 26 | 22,160,795 | 20,629,170 | 9,422,286 | 8,552,225 |
| Cost of sales | 27 | (13,315,084) | (12,584,740) | (4,932,857) | (4,767,484) |
| Gross profit | 8,845,711 | 8,044,430 | 4,489,429 | 3,784,741 | |
| Administrative expenses | 28 | (2,052,470) | (1,931,296) | (773,143) | (561,754) |
| Credit impairment losses | 29 | (92,441) | (36,907) | (52,808) | (19,907) |
| Other income | 152,585 | 340,571 | 65,674 | 69,846 | |
| Operating profit | 6,853,385 | 6,416,798 | 3,729,152 | 3,272,926 | |
| Finance income | 30 | 660,182 | 367,150 | 219,651 | 74,414 |
| Finance costs | 30 | (1,403,753) | (706,695) | (492,587) | (214,664) |
| Finance costs – net | 30 | (743,571) | (339,545) | (272,936) | (140,250) |
| Profit for the period before net movement in regulatory deferral account | 6,109,814 | 6,077,253 | 3,456,216 | 3,132,676 | |
| Net movement in regulatory deferral account balance | 24 | 20,227 | 396,457 | (66,006) | 39,820 |
| Profit for the period and net movement in regulatory deferral account | 6,130,041 | 6,473,710 | 3,390,210 | 3,172,496 |
Other comprehensive incomeItems that will not be reclassified to profit or loss
| Remeasurement of retirement benefit obligations | 20.1 | 11,257 | 1,283 | 2,699 | 3,166 |
|---|---|---|---|---|---|
| Debt instrument at FVOCI – change in fair value | 10 | 1,399 | (4,835) | 413 | (842) |
Items that may be reclassified to profit or loss
| Cash flow hedges – reclassified to profit or loss | (408,974) | 156,922 | (150,291) | (11,490) | |
|---|---|---|---|---|---|
| Cash flow hedges – effective portion of changes in fair value of derivative financial instruments | 9 | 1,270,693 | 3,534,204 | 1,069,676 | 440,709 |
| Other comprehensive income for the period | 874,375 | 3,687,574 | 922,497 | 431,543 | |
| Total comprehensive income for the period | 7,004,416 | 10,161,284 | 4,312,707 | 3,604,039 |
Profit for the period attributable to
| - Owners of the Company | 5,999,059 | 6,236,990 | 3,325,045 | 3,088,054 | |
|---|---|---|---|---|---|
| - Non-controlling interests | 130,982 | 236,720 | 65,165 | 84,442 | |
| 6,130,041 | 6,473,710 | 3,390,210 | 3,172,496 |
Total comprehensive income for the period attributable to
| - Owners of the Company | 6,453,378 | 8,176,680 | 3,803,031 | 3,317,923 | |
|---|---|---|---|---|---|
| - Non-controlling interests | 551,038 | 1,984,604 | 509,676 | 286,116 | |
| 7,004,416 | 10,161,284 | 4,312,707 | 3,604,039 |
Earnings per shareBasic earnings per share (AED) | 36 | 0.120 | 0.125 | 0.067 | 0.062
The independent auditors’ report on review of condensed consolidated interim financial information is set out on pages 1 and 2.
The notes on pages 8 to 40 form an integral part of this condensed consolidated interim financial information.
4
Page 7
Dubai Electricity and Water Authority (PJSC) and its subsidiaries Condensed consolidated interim statement of changes in equity
| Attributable to the Owners | Non-controlling interests AED’000 | Total equity AED’000 | |||||||
|---|---|---|---|---|---|---|---|---|---|
| Share capital AED’000 | Capital contribution AED’000 | General reserve AED’000 | Statutory reserve AED’000 | Hedging reserve AED’000 | Retained earnings AED’000 | Total AED’000 | |||
| At 1 January 2022 (Audited) | 500,000 | 40,037,040 | 53,343,435 | 355,467 | (1,236,145) | - | 92,999,797 | 591,911 | 93,591,708 |
| Total comprehensive income for the period | |||||||||
| Profit for the period | - | - | - | - | - | 6,236,990 | 6,236,990 | 236,720 | 6,473,710 |
| Other comprehensive income for the period | - | - | - | - | 1,942,176 | (2,486) | 1,939,690 | 1,747,884 | 3,687,574 |
| Total comprehensive income for the period | - | - | - | - | 1,942,176 | 6,234,504 | 8,176,680 | 1,984,604 | 10,161,284 |
| Transfer to retained earnings (refer note 18) | - | - | (43,343,435) | - | - | 43,343,435 | - | - | - |
| Transfer to statutory reserve | - | - | - | 305,452 | - | (305,452) | - | - | - |
| Transactions with the Owners | |||||||||
| Capital contribution – value of land (net) (refer note 6 (f)) | - | 5,845 | - | - | - | - | 5,845 | - | 5,845 |
| Capital contribution by non-controlling interests | - | - | - | - | - | - | - | 487,251 | 487,251 |
| Dividends paid (refer note 35) | - | - | (10,000,000) | - | - | - | (10,000,000) | (1,023,679) | (11,023,679) |
| At 30 September 2022 (Unaudited) | 500,000 | 40,042,885 | - | 660,919 | 706,031 | 49,272,487 | 91,182,322 | 2,040,087 | 93,222,409 |
The notes on pages 8 to 40 form an integral part of this condensed consolidated interim financial information.
5
Page 8
Dubai Electricity and Water Authority (PJSC) and its subsidiaries Condensed consolidated interim statement of changes in equity (continued)
| Attributable to the Owners | Non-controlling interests AED’000 | Total equity AED’000 | ||||||
|---|---|---|---|---|---|---|---|---|
| Share capital AED’000 | Capital contribution AED’000 | Statutory reserve AED’000 | Hedging reserve AED’000 | Retained earnings AED’000 | Total AED’000 | |||
| At 1 January 2023 (Audited) | 500,000 | 40,042,885 | 591,346 | 954,247 | 47,338,862 | 89,427,340 | 2,953,130 | 92,380,470 |
| Total comprehensive income for the period | ||||||||
| Profit for the period | - | - | - | - | 5,999,059 | 5,999,059 | 130,982 | 6,130,041 |
| Other comprehensive income for the period | - | - | - | 447,232 | 7,087 | 454,319 | 420,056 | 874,375 |
| Total comprehensive income for the period | - | - | - | 447,232 | 6,006,146 | 6,453,378 | 551,038 | 7,004,416 |
| Transactions with the Owners | ||||||||
| Capital contribution by non-controlling interests | - | - | - | - | - | - | 776,306 | 776,306 |
| Dividends (refer note 35) | - | - | - | - | (7,870,000) | (7,870,000) | (376,070) | (8,246,070) |
| At 30 September 2023 (Unaudited) | 500,000 | 40,042,885 | 591,346 | 1,401,479 | 45,475,008 | 88,010,718 | 3,904,404 | 91,915,122 |
The notes on pages 8 to 40 form an integral part of this condensed consolidated interim financial information.
6
Page 9
Dubai Electricity and Water Authority (PJSC) and its subsidiaries Condensed consolidated interim statement of cash flows
For the nine-month period ended 30 SeptemberNotes | 2023 AED’000 (Unaudited) | 2022 AED’000 (Unaudited)Net cash generated from operating activities | 33 | 9,848,212 | 9,094,309
Investing activities
| Purchase of property, plant and equipment net of movements in trade payables and other long-term liabilities | (4,439,879) | (6,993,518) | |
|---|---|---|---|
| Deposits with original maturity of greater than three months – placed during the period | (426,665) | (3,181,735) | |
| Deposits with original maturity of greater than three months – matured during the period | 2,331,243 | 732,583 | |
| Additions to investment property | (10,526) | - | |
| Purchase of intangible assets | 7 | (14,970) | (6,219) |
| Acquisition of subsidiary | 32 | (892,500) | - |
| Movement in other financial assets | 13 | 200,203 | (159,455) |
| Interest received | 557,935 | 135,841 | |
| Proceeds from disposal of property, plant and equipment | 4,448 | 243 | |
| Net cash used in investing activities | (2,690,711) | (9,472,260) |
Financing activities
| Repayments of borrowings | (2,606,664) | (3,615,736) | |
|---|---|---|---|
| Proceeds from borrowings | 1,378,773 | 17,155,590 | |
| Interest paid | (1,792,327) | (1,105,004) | |
| Capital contribution by non-controlling interests | 776,306 | 487,251 | |
| Payment of lease liabilities | (10,700) | (9,823) | |
| Dividend paid to the Owners | (4,770,000) | (10,000,000) | |
| Dividends paid to non-controlling interests | (189,070) | (1,023,679) | |
| Net cash (used in)/generated from financing activities | (7,213,682) | 1,888,599 |
| Net (decrease)/increase in cash and cash equivalents | (56,181) | 1,510,648 | |
|---|---|---|---|
| Cash and cash equivalents, beginning of period | 17 | 4,722,296 | 4,972,048 |
| Cash and cash equivalents, end of period | 17 | 4,666,115 | 6,482,696 |
Material non-cash transactions:
- There was no land transferred to the Group during the period (for nine-month period ended 30 September 2022: AED 6 million) (refer note 6).
The independent auditors’ report on review of condensed consolidated interim financial information is set out on pages 1 and 2.
The notes on pages 8 to 40 form an integral part of this condensed consolidated interim financial information.
7
Page 10
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial informationfor the nine-month period ended 30 September 2023 (unaudited)
1 Establishment and operations
Dubai Electricity and Water Authority (*DEWA” or “the Authority” or “the Company”) was incorporated
on | January 1992 in the Emirate of Dubai by a decree (“the Original Decree”) issued by H.H. The Ruler
of Dubai, effective 1 January 1992, as an independent public authority having the status of a body corporate, and financially and administratively independent from the Government. In accordance with the Original Decree, all rights, property and assets of Dubai Electricity Company (“DEC”) and Dubai Water Department (“the Department”) belonging to the Government, were vested in the Authority, and the Authority was held responsible for all liabilities and debts of DEC and the Department, of any kind whatsoever. Together, DEC and the Department formed DEWA from the effective date of the Original Decree.
The principal activities of the Authority, in accordance with the Original Decree and Decree No. 13 of 1999 which amended some of the provisions of the Original Decree, comprise water desalination and distribution and the generation, transmission and distribution of electricity, throughout the Emirate of Dubai. The registered address of the Authority is P.O. Box 564, Dubai, United Arab Emirates (“UAE”).
During the prior years, the Authority was wholly owned by the Government of Dubai which announced its plan to list the shares of the Authority on the Dubai Financial Market (DFM). In the year 2022, Department of Finance (DoF), Government of Dubai had sold 18% of its shareholding in the Authority through an Initial Public Offering (“IPO”). The Authority got listed on the Dubai Financial Market (DFM) and its shares started trading with effect from 12 April 2022.
The ownership structure of the Authority is as follows:
Ownership %
Department of Finance (DoF), Government of Dubai 82%
Local and international investors (including institutional and retail
investors) 18%100%
DEWA and its subsidiaries are collectively referred to as “the Group”. The Group either directly or indirectly controls following significant subsidiaries, which are domiciled in UAE:
Percentage of beneficial
ownership30 September 31 December
2023 2022
Name of the entity (Unaudited) (Audited) Principal business activities
Al Etihad Energy Services 100 100 Implement energy efficiency measures
Company LLC in buildings
Etihad Clean Energy 100 100 Buildings energy efficiency services, Development Company LLC solar energy systems rental and solar
energy systems installation
Jumeirah Energy International 100 100 Holding Company Holdings LLC (JEIHL)
Jumeirah Energy International 100 100 Holding Company LLC (JEI)
Mai Dubai LLC 100 100 Purification and sale of potable waterHassyan Energy | Holdings 100 100 Holding CompanyLLCShuaa Energy 2 Holdings LLC 100 100 Holding Company
Page 11
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
1 Establishment and operations (continued)
| Percentage of beneficial ownership | |||
|---|---|---|---|
| 30 September 2023 (Unaudited) | 31 December 2022 (Audited) | Principal business activities | |
| Name of the entity | |||
| Shuaa Energy 3 Holdings LLC | 100 | 100 | Holding Company |
| Jumeirah Energy International Capital Holding LLC | 100 | 100 | Holding Company |
| Jumeirah Energy International Silicon Valley LLC | 100 | 100 | Holding Company |
| Noor Energy 1 Holdings LLC | 100 | 100 | Holding Company |
| Data Hub Integrated Solutions LLC (MORO) | 100 | 100 | Established to provide services including IT, and infrastructure, networking and computer system housing services |
| Digital DEWA LLC | 100 | 100 | Investment in commercial, industrial, retail trade and energy enterprises and management |
| Infra X | 100 | 100 | To provide services including IT and computer housing services |
| Dubai Green Fund Investments LLC | 100 | 100 | To invest and manage commercial, industrial, retail trade and energy enterprises |
| Utilities Management Company LLC | 78 | 78 | Holding Company |
| Emirates Central Cooling Systems Corporation PJSC (EMPOWER) | 56 | 56 | Provision of district cooling services, management, maintenance of central cooling plants and related distribution networks |
| EMPOWER FM LLC | 56 | 56 | Air conditioning, ventilation and air filtration system, installation and maintenance |
| EMPOWER Engineering & Consultancy LLC | 56 | 56 | Project development consultant services |
| Palm Utilities LLC | 56 | 56 | Establish and operate district cooling projects and provide air conditioning, ventilator and refrigeration services |
| Palm District Cooling LLC (PDC) | 56 | 56 | Establish and operate district cooling projects and provide air conditioning, ventilator and refrigeration services. |
| EMPOWER Logstor LLC | 54.3 | 54.3 | Manufacturing of pre-insulated pipes, mainly for district cooling |
| Shuaa Energy 2 P.S.C | 60 | 60 | Establish and provide full range of services for generation of electricity |
| Innogy International Middle East LLC | 51 | 51 | Energy projects consultancy, desalination and sewage treatment plants operations and maintenance |
| Shuaa Energy 1 P.S.C | 51 | 51 | Establish and provide full range of services for generation of electricity |
| Hassyan Energy Phase 1 P.S.C | 51 | 51 | Establish and provide full range of services for generation of electricity |
9
Page 12
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
1 Establishment and operations (continued)
Percentage of beneficialownership30 September 31 December2023 2022
| Name of the entity | (Unaudited) | (Audited) | Principal business activities |
|---|---|---|---|
| Noor Energy 1 P.S.C | 51 | 51 | Establish and provide full range of services for generation of electricity |
| Digital X LLC | 100 | 100 | Establish and provide full range of services for information technology, data entry, network consultancies |
| Smart Energy X LLC | 100 | 100 | Establish and provide full range of services for parking management electronic systems installation and maintenance |
| Shuaa Energy 3 P.S.C | 60 | 60 | Establish and provide full range of services for generation of electricity |
| Forward Investments Limited | 100 | 100 | Holding Company |
| Dubai Carbon Centre of Excellence | 100 | 100 | Energy projects engineering consultancy and carbon control systems trading |
| SecureX | 100 | 100 | Computer systems housing services, communication equipment, software design, data classification & analysis services, IT infrastructure, data centre co-location services and information technology network services |
| Space D | 100 | 100 | Managing & operating satellites & provision satellite services, wired & wireless communication systems installation and space situational tracking, monitoring & awareness services |
| EMPOWER Snow LLC | 56 | 56 | Establish and operate district cooling projects and provide air-conditioning, ventilation and refrigeration services |
| Hassyan Water Company A Holdings LLC * | 100 | - | Holding Company |
| Shuaa Energy 4 Holding LLC * | 100 | - | Holding Company |
* During the period ended 30 September 2023, on 13 September 2023 the Group has incorporated two new entities, each with 100% ownership.
10
Page 13
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued)
for the nine-month period ended 30 September 2023 (unaudited)
2 Summary of significant accounting policies
The principal accounting policies applied by the Group in the preparation of these condensed consolidated interim financial information are set out below. These policies have been consistently applied to all the periods presented, except below stated policy for current and deferred income tax.
2.1 Income tax
Income tax expense comprises current and deferred tax. It is recognised in profit or loss except to the extent that it relates to a business combination, or items recognised directly in equity or in OCI. Refer note 38 for application UAE Tax law related to current and deferred tax.
Current tax
Current tax comprises the expected tax payable or receivable on the taxable income or loss for the year and any adjustment to the tax payable or receivable in respect of previous years. The amount of current tax payable or receivable is the best estimate of the tax amount expected to be paid or received that reflects uncertainty related to income taxes, if any. It is measured using tax rates enacted or substantively enacted at the reporting date. Current tax also includes any tax arising from dividends.
Current tax assets and liabilities are offset when there is a legally enforceable right to set off recognised amounts and intends either to settle on a net basis, or to realise the asset and settle the liability simultaneously.
Deferred Tax
Deferred tax is recognised in respect of temporary differences between the carrying amounts of assets and liabilities for financial reporting purposes and the amounts used for taxation purposes. Deferred tax is not recognised for:
- temporary differences on the initial recognition of assets or liabilities in a transaction that:
- _ is not a business combination; and
- at the time of the transaction (i) affects neither accounting nor taxable profit or loss and (ii) does not give rise to equal taxable and deductible temporary differences:
- temporary differences related to investments in subsidiaries, associates and joint arrangements to the extent that the Group is able to control the timing of the reversal of the temporary differences and it is probable that they will not reverse in the foreseeable future; and
- taxable temporary differences arising on the initial recognition of goodwill.
Deferred tax assets are recognised for unused tax losses, unused tax credits and deductible temporary differences to the extent that it is probable that future taxable profits will be available against which they can be used. Future taxable profits are determined based on the reversal of relevant taxable temporary differences. If the amount of taxable temporary differences is insufficient to recognise a deferred tax asset in full, then future taxable profits, adjusted for reversals of existing temporary differences, are considered, based on the business plans for individual subsidiaries in the Group. Deferred tax assets are reviewed at each reporting date and are reduced to the extent that it is no longer probable that the related tax benefit will be realised; such reductions are reversed when the probability of future taxable profits improves.
11
Page 14
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
2 Summary of significant accounting policies (continued)
2.1 Current and deferred income tax (continued)
Deferred Tax (continued)
The measurement of deferred tax reflects the tax consequences that would follow from the manner in which the Group expects, at the reporting date, to recover or settle the carrying amount of its assets and liabilities.
Deferred tax assets and liabilities are offset when there is a legally enforceable right to set off current tax asset against current tax liabilities and when they relate to income taxes levied by the same taxation authority and the Group intends to settle its current tax assets and current tax liabilities on a net basis.
2.2 Basis of preparation
These condensed consolidated interim financial information for the nine-month period ended 30 September 2023 have been prepared in accordance with International Accounting Standard 34 ‘Interim Financial Reporting’.
The Group’s condensed consolidated interim financial information are presented in UAE Dirhams (AED), which is also the Group’s functional currency. Subsidiaries and joint ventures determine their own functional currency and items included in the financial information of these companies are measured using that functional currency. All financial information presented in AED has been rounded to the nearest thousand.
The accounting policies applied are consistent with those of the annual consolidated financial statements for the year ended 31 December 2022, as described in those financial statements, except for certain new and revised standards that became effective in the current period (if applicable). This condensed consolidated interim financial information does not include all the notes of the type normally included in the annual consolidated financial statements. Accordingly, this condensed consolidated interim financial information should be read in conjunction with the annual consolidated financial statements for the year ended 31 December 2022.
The preparation of condensed consolidated interim financial information in conformity with International Financial Reporting Standards (“IFRS”) requires the use of certain critical accounting estimates. It also requires management to exercise its judgement in the process of applying the Group’s accounting policies.
The areas involving a higher degree of judgement or complexity, or areas where assumptions and estimates are significant to the Group’s condensed consolidated interim financial information are consistent with the annual consolidated financial statements for the year ended 31 December 2022.
Results for the nine-month period ended 30 September 2023 are not necessarily indicative of the results that may be expected for the year ending 31 December 2023.
2.3 Basis of measurement
This condensed consolidated interim financial information has been prepared on a historical cost basis except for certain financial assets and financial liabilities measured at fair value.
2.4 Use of estimates and judgments
In preparing the condensed consolidated interim financial information, management has made judgments,
estimates and assumptions that affect the application of the Group's accounting policies and the reported amount of assets and liabilities, income and expenses.
12
Page 15
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
2 Summary of significant accounting policies (continued)
2.4 Use of estimates and judgments (continued)
Estimates and underlying assumptions are reviewed on an ongoing basis. Revisions to accounting estimates are recognised in the period in which the estimate is revised and in any future periods affected. In preparing this condensed consolidated interim financial information, the significant judgments made by management in applying the Group’s accounting policies and the key sources of estimation and uncertainty were the same as those that applied to the annual consolidated financial statements as at and for the year ended 31 December 2022.
2.5 New standards, amendments and interpretations
New standards, amendments and interpretations issued but not yet effective
A number of new standards are effective for annual periods beginning after 1 January 2023 and earlier application is permitted, however, the Group has not early adopted the new or amended standards in preparing the condensed consolidated interim financial information.
The following amended standards and interpretations are not expected to have a significant impact on the Group’s condensed consolidated interim financial information:
| Effective date
| Non-current liabilities with covenants – Amendments to IAS 1 and classifications of liabilities as Current or Non-current – Amendments to IAS 1 | 1 January 2024 |
| Lease liabilities in a Sale and Leaseback – Amendments to IFRS 16 | 1 January 2024 |
| Supplier Finance Arrangements – Amendments to IAS 7 and IFRS 7 | 1 January 2024 |
| Lack of Exchangeability – Amendments to IAS 21 | 1 January 2025 |
| Sale of contribution of assets between an Investor and its Associate or Joint Venture –Amendments to IFRS 10 and IAS 28 | Available for optional adoption/effective date deferred indefinitely |
New standards, amendments and interpretations effective during the period
The following new or amended standards that are required to be adopted in annual periods beginning on 1 January 2023 and do not have a significant impact on the Group's condensed consolidated interim financial information:
| Effective date
| IFRS 17 Insurance Contracts | 1 January 2023 |
| Disclosure of Accounting Policies (Amendments to IAS 1 and IFRS Practice Statement 2) | 1 January 2023 |
| Definition of Accounting Estimates (Amendments to IAS 8) | 1 January 2023 |
| Deferred Tax related to Assets and Liabilities arising from a Single Transaction (Amendments to IAS 12) | 1 January 2023 |
| International Tax Reform – Pillar Two Model Rules (Amendments to IAS 12) | 23 May 2023 |
13
Page 16
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
3 Financial risk management
3.1 Financial risk factors
The Group’s activities expose it to a variety of financial risks: market risk (including currency risk, price risk and cash flow and fair value interest rate risk), credit risk and liquidity risk.
The condensed consolidated interim financial information does not include all financial risk management information and disclosures required in the annual consolidated financial statements. Accordingly, this condensed consolidated interim financial information should be read in conjunction with the annual consolidated financial statements for the year ended 31 December 2022. There have been no changes in the risk management department or in any risk management policies since the year end.
3.2 Fair value estimation
All financial assets and liabilities are initially measured at cost, which is the fair value of the consideration given and received respectively. These financial assets and liabilities are subsequently measured at amortised cost.
The carrying value of financial assets and financial liabilities approximates their fair value except derivatives which are the only financial instruments which are carried at fair value and fall into Level 2 of the fair value hierarchy.
To provide an indication about the reliability of the inputs used in determining fair value disclosed in this condensed consolidated interim financial information, the Group has classified its financial instruments into three levels described below:
a. Quoted prices (unadjusted) in active markets for identical assets or liabilities (Level 1).
b. Inputs other than quoted prices included within Level | that are observable for the asset or liability,
either directly (that is, as prices) or indirectly (that is, derived from prices) (Level 2); and
Ci Inputs for the asset or liability that are not based on observable market data (that is, unobservable inputs) (Level 3).
4 Seasonality of operations
Due to the seasonal nature of the operations of the Group, higher revenues and operating profits are usually
expected in the second half of the year than the first six months. In the year ended 31 December 2022, 44%
of revenue accumulated in the first half of the year, with 56% accumulating in the second half.
14
Page 17
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued)
for the nine-month period ended 30 September 2023 (unaudited)
5 Segment reporting
Information about reportable segments and reconciliation of information on reportable segments to the amount reported in the annual consolidated financial statements
Information related to each reportable segment is set out below. Segment profit/(loss) before tax is used to measure performance because management believes that this information is the most relevant in evaluating the results of the respective segments relative to other entities that operate in similar industries.
| DEWA | EMPOWER | IPP | Others | Eliminations | Total | |
| 30 September 2023 (Unaudited) | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 |
Segment assets
| Non-current assets | 134,329,583 | 8,748,785 | 32,889,402 | 2,440,467 | (17,140,615) | 161,267,622 |
|---|---|---|---|---|---|---|
| Current assets | 15,292,482 | 1,347,457 | 3,242,564 | 4,719,408 | (2,369,560) | 22,232,351 |
| Total assets | 149,622,065 | 10,096,242 | 36,131,966 | 7,159,875 | (19,510,175) | 183,499,973 |
Segment liabilities
| Non-current liabilities | 41,986,966 | 4,864,130 | 29,591,571 | 98,273 | (12,838,892) | 63,702,048 |
|---|---|---|---|---|---|---|
| Current liabilities | 22,060,401 | 2,192,320 | 2,097,317 | 3,848,957 | (2,391,308) | 27,807,687 |
| Regulatory deferral account credit balance | 75,116 | - | - | - | - | 75,116 |
| Total liabilities and regulatory deferral account credit balance | 64,122,483 | 7,056,450 | 31,688,888 | 3,947,230 | (15,230,200) | 91,584,851 |
| Net segment assets | 85,499,582 | 3,039,792 | 4,443,078 | 3,212,645 | (4,279,975) | 91,915,122 |
| DEWA | EMPOWER | IPP | Others | Eliminations | Total | |
| 31 December 2022 (Audited) | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 |
Segment assets
| Non-current assets | 132,111,470 | 7,776,101 | 31,016,060 | 2,194,551 | (14,583,583) | 158,514,599 |
|---|---|---|---|---|---|---|
| Current assets | 14,787,377 | 1,878,874 | 2,825,200 | 4,133,381 | (1,429,135) | 22,195,697 |
| Total assets | 146,898,847 | 9,654,975 | 33,841,260 | 6,327,932 | (16,012,718) | 180,710,296 |
Segment liabilities
| Non-current liabilities | 47,483,807 | 4,859,945 | 27,933,985 | 135,690 | (9,254,325) | 71,159,102 |
|---|---|---|---|---|---|---|
| Current liabilities | 12,020,925 | 1,760,288 | 2,597,068 | 3,237,266 | (2,540,166) | 17,075,381 |
| Regulatory deferral account credit balance | 95,343 | - | - | - | - | 95,343 |
| Total liabilities and regulatory deferral account credit balance | 59,600,075 | 6,620,233 | 30,531,053 | 3,372,956 | (11,794,491) | 88,329,826 |
| Net segment assets | 87,298,772 | 3,034,742 | 3,310,207 | 2,954,976 | (4,218,227) | 92,380,470 |
15
Page 18
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
5 Segment reporting (continued)Other segment information
| DEWA | EMPOWER | IPP | Others | Eliminations | Total | |
|---|---|---|---|---|---|---|
| For the nine-month period ended 30 September 2023 (Unaudited) | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 |
| Revenue | 20,421,715 | 2,293,172 | 1,312,185 | 1,076,406 | (2,942,683) | 22,160,795 |
| Cost of sales | (12,506,642) | (1,321,007) | (971,783) | (591,933) | 2,076,281 | (13,315,084) |
| Gross profit | 7,915,073 | 972,165 | 340,402 | 484,473 | (866,402) | 8,845,711 |
| Administrative expenses | (1,995,209) | (168,064) | (49,514) | (360,974) | 521,291 | (2,052,470) |
| Credit impairment losses | (91,272) | - | - | (1,169) | - | (92,441) |
| Other income | 600,145 | 4,525 | 12,209 | 20,110 | (484,404) | 152,585 |
| Operating profit | 6,428,737 | 808,626 | 303,097 | 142,440 | (829,515) | 6,853,385 |
| Finance income | 280,836 | 39,208 | 297,139 | 125,420 | (82,421) | 660,182 |
| Finance costs | (658,988) | (162,940) | (945,820) | (22,799) | 386,794 | (1,403,753) |
| Finance (costs)/income – net | (378,152) | (123,732) | (648,681) | 102,621 | 304,373 | (743,571) |
| Net movement in regulatory deferral account credit balance | 20,227 | - | - | - | - | 20,227 |
| Profit/(loss) for the period | 6,070,812 | 684,894 | (345,584) | 245,061 | (525,142) | 6,130,041 |
| Other comprehensive income | - | 12,656 | 861,719 | - | - | 874,375 |
| Total comprehensive income for the period | 6,070,812 | 697,550 | 516,135 | 245,061 | (525,142) | 7,004,416 |
| DEWA | EMPOWER | IPP | Others | Eliminations | Total | |
|---|---|---|---|---|---|---|
| For the nine-month period ended 30 September 2022 (Unaudited) | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 |
| Revenue | 19,010,585 | 2,073,074 | 869,824 | 853,988 | (2,178,301) | 20,629,170 |
| Cost of sales | (11,757,842) | (1,163,761) | (550,262) | (541,421) | 1,428,546 | (12,584,740) |
| Gross profit | 7,252,743 | 909,313 | 319,562 | 312,567 | (749,755) | 8,044,430 |
| Administrative expenses | (1,889,393) | (153,611) | (19,124) | (322,361) | 453,193 | (1,931,296) |
| Credit impairment losses | (30,464) | (7,395) | - | 952 | - | (36,907) |
| Other income | 2,728,132 | 4,812 | 54,199 | 26,603 | (2,473,175) | 340,571 |
| Operating profit | 8,061,018 | 753,119 | 354,637 | 17,761 | (2,769,737) | 6,416,798 |
| Finance income | 130,613 | 24,172 | 209,963 | 88,237 | (85,835) | 367,150 |
| Finance costs | (410,088) | (45,249) | (516,459) | (22,033) | 287,134 | (706,695) |
| Finance (costs)/income – net | (279,475) | (21,077) | (306,496) | 66,204 | 201,299 | (339,545) |
| Net movement in regulatory deferral account credit balance | 396,457 | - | - | - | - | 396,457 |
| Profit for the period | 8,178,000 | 732,042 | 48,141 | 83,965 | (2,568,438) | 6,473,710 |
| Other comprehensive income/(loss) | - | (3,552) | 3,691,126 | - | - | 3,687,574 |
| Total comprehensive income for the period | 8,178,000 | 728,490 | 3,739,267 | 83,965 | (2,568,438) | 10,161,284 |
16
Page 19
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
5 Segment reporting (continued)
Other segment information
| DEWA | EMPOWER | IPP | Others | Eliminations | Total | |
|---|---|---|---|---|---|---|
| For the nine-month period ended 30 September 2023 (Unaudited) | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 |
| Capital expenditure (property, plant and equipment) | 3,365,293 | 201,916 | 1,633,013 | 12,973 | - | 5,213,195 |
| Depreciation (property, plant and equipment) | 3,429,465 | 257,309 | 317,276 | 298,728 | (12,402) | 4,290,376 |
| DEWA | EMPOWER | IPP | Others | Eliminations | Total | |
|---|---|---|---|---|---|---|
| For the year ended 31 December 2022 (Audited) | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 | AED’000 |
| Capital expenditure (property, plant and equipment) | 4,849,905 | 332,887 | 4,767,497 | 169,314 | - | 10,119,603 |
| Depreciation (property, plant and equipment) | 4,734,106 | 311,807 | 237,337 | 98,332 | (6,843) | 5,374,739 |
17
Page 20
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
6 Property, plant and equipment
| Land and buildings AED’000 | Right-of-use assets AED’000 | Generation and desalination plants AED’000 | Transmission and distribution networks AED’000 | Other equipment and assets AED’000 | Capital work in progress AED’000 | Total AED’000 | |
|---|---|---|---|---|---|---|---|
| Year ended 31 December 2022 | |||||||
| Opening net book amount (Audited) | 39,088,117 | 23,856 | 33,437,273 | 48,574,168 | 804,203 | 27,544,444 | 149,472,061 |
| Additions | 7,842 | 17,037 | 107,939 | 413,280 | 111,862 | 9,461,643 | 10,119,603 |
| Transfer to right of use assets | - | 18,316 | (7,780) | - | (10,536) | - | - |
| Reversal of impairment | - | - | - | - | - | 12,727 | 12,727 |
| Reclassification to investment property (refer note 11) | (2,536) | - | - | - | - | (70,323) | (72,859) |
| Transfers | 604,118 | - | 2,147,084 | 4,288,607 | 119,198 | (7,159,007) | - |
| Transfers to intangible assets (refer note 7) | - | - | - | - | (320) | (19,335) | (19,655) |
| Modification of right-of-use assets | - | (11,558) | - | - | - | - | (11,558) |
| Disposals, net | - | - | (3,853) | (92,247) | (69) | - | (96,169) |
| Depreciation | (365,773) | (12,827) | (2,048,742) | (2,620,607) | (326,790) | - | (5,374,739) |
| Closing net book amount (Audited) | 39,331,768 | 34,824 | 33,631,921 | 50,563,201 | 697,548 | 29,770,149 | 154,029,411 |
| At 31 December 2022 | |||||||
| Cost | 43,600,056 | 64,678 | 55,574,765 | 78,069,768 | 3,478,813 | 29,770,149 | 210,558,229 |
| Accumulated depreciation | (4,268,288) | (29,854) | (21,942,844) | (27,506,567) | (2,781,265) | - | (56,528,818) |
| Net book amount (Audited) | 39,331,768 | 34,824 | 33,631,921 | 50,563,201 | 697,548 | 29,770,149 | 154,029,411 |
| Period ended 30 September 2023 | |||||||
| Opening net book amount (Audited) | 39,331,768 | 34,824 | 33,631,921 | 50,563,201 | 697,548 | 29,770,149 | 154,029,411 |
| Additions | 410 | 2,288 | 109,107 | 89,136 | 111,568 | 4,900,686 | 5,213,195 |
| Transfers | 223,308 | - | 10,214,207 | 1,680,039 | 179,643 | (12,297,197) | - |
| Transfers to intangible assets (refer note 7) | - | - | - | - | - | (28,661) | (28,661) |
| Disposals, net | - | - | (1,803) | (2,095) | (18) | - | (3,916) |
| Depreciation | (267,615) | (10,663) | (1,782,206) | (2,002,173) | (227,719) | - | (4,290,376) |
| Closing net book amount (Unaudited) | 39,287,871 | 26,449 | 42,171,226 | 50,328,108 | 761,022 | 22,344,977 | 154,919,653 |
| At 30 September 2023 | |||||||
| Cost | 43,823,774 | 66,966 | 65,709,549 | 79,836,782 | 3,750,920 | 22,344,977 | 215,532,968 |
| Accumulated depreciation | (4,535,903) | (40,517) | (23,538,323) | (29,508,674) | (2,989,898) | - | (60,613,315) |
| Net book amount (Unaudited) | 39,287,871 | 26,449 | 42,171,226 | 50,328,108 | 761,022 | 22,344,977 | 154,919,653 |
18
Page 21
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
6
(a)
(b)
(c)
(d)
(e)
(f)
(g)
Property, plant and equipment (continued)
The Group has engaged in a joint operation pertaining to Emirates National Grid Corporation (“ENGC”). The Group’s share in the carrying amount of ENGC’s assets as at 30 September 2023 is AED 103 million (37 December 2022: AED 109 million) and is included under transmission and distribution networks.
During 2008, by way of a Decree issued by H.H. The Ruler of Dubai, all existing plots of land held by the Authority were transferred to the Authority. As a result, the Authority has capitalised the plots of land on the basis of valuations (i.e. valuation based on use limitations) obtained from the Land Department of the Government of Dubai, which is considered the deemed cost and has been treated as a capital contribution by the Government of Dubai.
On initial recognition:
- The valuation of land is done based on the valuation certificate issued by Dubai Land Department and such valuation is considered for the lands issued in the same area/zone in future.
- The valuation of land so adopted (original value) will not be changed even if the area/zone is changed by the Dubai Land Department subsequently.
As per communication from Department of Finance, Government of Dubai, effective 10 March 2022, the new land policy in respect of allotment and granting of lands in the Emirate of Dubai by the Dubai Land Department to the Authority will be in consideration for a rental value of AED | per plot per annum for 30 years. This policy shall apply to all future lands that will be allotted to the Authority, but not on the existing lands that are currently being governed under the existing regime. The Department of Finance, Government of Dubai and the Authority shall coordinate to take all actions and procedures to procure the issuance of a decree that shall formalize the proposed policy for all future lands.
Capital work in progress mainly comprises construction of additional electricity generation, water desalination facilities, transmission and distribution networks and district cooling facilities.
The interest rate used for capitalizing the borrowing cost is LIBOR plus applicable margin. The interest on borrowings capitalised using this interest rate is AED 433 million for the nine- month period ended 30 September 2023 (37 December 2022: AED 1,164 million) (refer note 30).
Right-of-use assets mainly represents vehicles and other equipment as of the reporting date.
During the current period, the Group did not receive any land from the Land Department of the Government of Dubai (3/ December 2022: AED 65 million (net)).
The carrying value of property, plant and equipment, pledged as collateral on borrowings, amounts to AED 31,032 million (37 December 2022: AED 27,886 million) (refer note 19).
19
Page 22
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
6 Property, plant and equipment (continued)
(h) Depreciation is allocated as detailed below:
| For the nine-month period ended 30 September | 2023 AED’000 (Unaudited) | 2022 AED’000 (Unaudited) |
|---|---|---|
| Cost of sales | ||
| - Generation, desalination and other direct expenditure (refer note 27.1) | 1,874,112 | 1,654,360 |
| - Transmission and distribution expenditure (refer note 27.2) | 2,209,963 | 2,114,637 |
| Administrative expenses (refer note 28) | 206,301 | 224,099 |
| 4,290,376 | 3,993,096 |
7 Intangible assets
| Computer software AED’000 | Others AED’000 | Total AED’000 | |
|---|---|---|---|
| Year ended 31 December 2022 | |||
| Opening net book amount (Audited) | 165,281 | 364,296 | 529,577 |
| Additions | 8,627 | - | 8,627 |
| Transfer from property, plant and equipment (refer note 6) | 19,655 | - | 19,655 |
| Amortisation | (74,579) | (12,157) | (86,736) |
| Closing net book amount (Audited) | 118,984 | 352,139 | 471,123 |
| At 31 December 2022 | |||
| Cost | 551,373 | 364,696 | 916,069 |
| Accumulated amortisation | (432,389) | (12,557) | (444,946) |
| Net book amount (Audited) | 118,984 | 352,139 | 471,123 |
| Computer software AED’000 | Others AED’000 | Total AED’000 | |
|---|---|---|---|
| Period ended 30 September 2023 | |||
| Opening net book amount (Audited) | 118,984 | 352,139 | 471,123 |
| Additions | 14,970 | - | 14,970 |
| Transfer from property, plant and equipment (refer note 6) | 28,661 | - | 28,661 |
| Amortisation (refer notes 27.1 and 28) | (49,262) | (9,117) | (58,379) |
| Closing net book amount (Unaudited) | 113,353 | 343,022 | 456,375 |
| At 30 September 2023 | |||
| Cost | 595,004 | 364,696 | 959,700 |
| Accumulated amortisation | (481,651) | (21,674) | (503,325) |
| Net book amount (Unaudited) | 113,353 | 343,022 | 456,375 |
During the current period, amortisation expense of AED 58 million (for the nine-month period ended 30 September 2022: AED 61 million) is included in cost of sales and administrative expenses (refer notes 27.1 and 28).
20
Page 23
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued)
for the nine-month period ended 30 September 2023 (unaudited)
8 Investments accounted for using the equity method
The following table outlines the Group’s investments in joint ventures. All joint ventures are accounted for under the equity method of accounting and are immaterial to the Group individually.
30 September 2023 AED’000 (Unaudited) | 31 December 2022 AED’000 (Audited)Investment in joint ventures | 640 | 640
The Group has either directly or indirectly the following joint ventures. The entities listed below have share capital solely consisting of ordinary shares, which are held directly by the Group.
| Name of the entity | Country of incorporation | Effective % of holding 2023 | Effective % of holding 2022 | Carrying value 30 September 2023 AED’000 (Unaudited) | Carrying value 31 December 2022 AED’000 (Audited) |
|---|---|---|---|---|---|
| Utility Management LLC | UAE | 50 | 50 | 490 | 490 |
| Etihad Smart Energy Solutions LLC | UAE | 50 | 50 | 150 | 150 |
| 640 | 640 |
9 Derivative financial instruments
The Group is exposed to interest rate movements on various borrowings maturing between 2017 and 2042. Some of the Group’s subsidiaries have entered into a series of interest rate swaps for the duration of the borrowings to mitigate the risk of variation in future interest rates. These interest rate swaps were designated as cash flow hedges and were assessed to be highly effective for majority contracts. Net unrealised gain of AED 1,271 million (for the nine-month period ended 30 September 2022: AED 3,534 million) relating to these hedging instruments is included in other comprehensive income.
The tables below show a summary of the hedged items, the hedging instruments and their fair values. The notional amounts indicate the amount outstanding at the period end.
| Description of the hedged item | Hedging instrument | Notional amount AED’000 | Positive fair value AED’000 | Negative fair value AED’000 |
|---|---|---|---|---|
| 30 September 2023 (Unaudited): | ||||
| Interest payments on floating rate loans | Interest rate swap | 21,243,495 | 2,649,904 | 808 |
| 31 December 2022 (Audited): | ||||
| Interest payments on floating rate loans | Interest rate swap | 31,125,023 | 1,786,908 | 4,578 |
21
Page 24
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued)
for the nine-month period ended 30 September 2023 (unaudited)
9 Derivative financial instruments (continued)
The following table presents the Group’s derivative assets and liabilities that are measured at fair value:
| Level 1 AED’000 | Level 2 AED’000 | Level 3 AED’000 | Total AED’000 | |
|---|---|---|---|---|
| 30 September 2023 (Unaudited) | ||||
| Assets measured at fair value | ||||
| Derivative financial instruments (current portion) | - | 641,107 | - | 641,107 |
| Derivative financial instruments (non-current portion) | - | 2,008,797 | - | 2,008,797 |
| Liabilities measured at fair value | ||||
| Derivative financial instruments (current portion) | - | - | - | - |
| Derivative financial instruments (non-current portion) | - | 808 | - | 808 |
| 31 December 2022 (Audited) | ||||
| Assets measured at fair value | ||||
| Derivative financial instruments (current portion) | - | 492,106 | - | 492,106 |
| Derivative financial instruments (non-current portion) | - | 1,294,802 | - | 1,294,802 |
| Liabilities measured at fair value | ||||
| Derivative financial instruments (current portion) | - | - | - | - |
| Derivative financial instruments (non-current portion) | - | 4,578 | - | 4,578 |
Interest rate swaps were measured primarily using valuations provided by the financial institutions based on the observable spot exchange rates and the yield curves of the respective swap contracts and were categorised in Level 2 hierarchy.
22
Page 25
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued)
for the nine-month period ended 30 September 2023 (unaudited)
10 Financial assets at fair value through other comprehensive income (FVOCI)
| 30 September 2023 AED’000 (Unaudited) | 31 December 2022 AED’000 (Audited) | |
|---|---|---|
| At the beginning of the period/year | 52,911 | 58,113 |
| Fair value adjustment during the period/year | 1,399 | (5,202) |
| At the end of the period/year | 54,310 | 52,911 |
Financial assets at fair value through other comprehensive income pertains to an investment in Tier 1 Capital Certificates ("the Bonds") issued at their par value. The Bonds are listed perpetual instruments and carry non-cumulative interest at a rate of 6% per annum payable every six months at the discretion of the issuer. The Group has classified them as financial assets at fair value through other comprehensive income under IFRS 9 as the Bonds are not held for trading.
During the current period, gain recognised in other comprehensive income amounted to AED 1 million (30 September 2022: loss of AED 5 million).
11 Investment property
30 September 2023 AED’000 (Unaudited) | 31 December 2022 AED’000 (Audited)Property under development | 83,385 | 72,859
The movement in property under development is as follows:
| 30 September 2023 AED’000 (Unaudited) | 31 December 2022 AED’000 (Audited) | |
|---|---|---|
| At the beginning of the period/year | 72,859 | - |
| Addition during the period/year | 10,526 | - |
| Reclassification from property, plant and equipment (refer note 6) | - | 72,859 |
| At the end of the period/year | 83,385 | 72,859 |
The Group’s subsidiary started construction of its head quarter project in 2021. The project consists of two towers with common area and retail outlets.
During the previous year, management revisited its plan of occupation and concluded to occupy only one tower for its use along with its related common area. As a result, the carrying amount of one tower and related areas were transferred to investment property from property, plant and equipment (refer note 6).
The fair value of investment property approximates to the carrying value.
23
Page 26
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
12 Other assets
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Advance to suppliers | 1,343,907 | 1,222,498 |
| Prepayments | 160,231 | 44,244 |
| 1,504,138 | 1,266,742 | |
| Less: non-current portion | (996,600) | (1,134,897) |
| Current portion | 507,538 | 131,845 |
13 Other financial assets
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| UAE National Bonds and Sukuk Bonds | 840,935 | 1,041,138 |
| Other receivables | 5,700,650 | 3,598,489 |
| Less: provision for impairment on other receivables | (47,913) | (47,913) |
| 6,493,672 | 4,591,714 | |
| Less: non-current portion | (2,747,862) | (1,457,956) |
| Current portion | 3,745,810 | 3,133,758 |
Other financial assets include investment in UAE National Bonds and Sukuk Bonds amounting to AED 841 million (31 December 2022: AED 1,041 million), which have a maturity of 12 months from the date of purchase. UAE National Bonds carry an interest rate ranging from 3% to 5.25% per annum (31 December 2022: 3% to 5.25% per annum).
Other receivables mainly include investment in debt instruments, financial assets under IFRIC 12, housing and sewerage fee receivable on behalf of a related party and interest receivable on bank deposits.
During the current period, in EMPOWER there is an addition of financial asset from Dubai Aviation City Corporation DACC (grantor) under IFRIC 12 as a result of acquisition of DXB Cool (refer note 32). The financial asset is initially recognised at fair value and subsequently measured at amortised cost. The fair value of the financial asset is the transaction price which is mutually agreed between the market participants through a competitive bidding process. The fair value of the financial assets at amortised cost in relation to acquisition of DXB Cool as at 30 September 2023 amounts to AED 1,047 million, categorised within level 3 of the fair value hierarchy. The fair value is determined using the discounted cash flow techniques, the inputs into the valuation techniques includes contractual cash flows and interest rates.
As at 30 September 2023, other receivables amounting to AED 5,652 million (31 December 2022: AED 3,550 million) are not impaired except for an amount of AED 48 million (31 December 2022: AED 48 million). The carrying amount of the Group's other receivables approximates its fair value.
24
Page 27
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
14 Inventories
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Consumables and repair spares | 644,859 | 657,301 |
| Less: provision for slow moving and obsolete inventory | (228,035) | (220,021) |
| 416,824 | 437,280 | |
| Fuel | 997,697 | 1,007,936 |
| 1,414,521 | 1,445,216 |
14.1 Movement in provision for slow moving and obsolete inventory
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| At the beginning of the period/year | 220,021 | 205,653 |
| Charge for the period/year | 8,014 | 14,368 |
| At the end of the period/year | 228,035 | 220,021 |
15 Trade receivables
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Trade receivables | 4,037,946 | 3,699,427 |
| Accrued revenue | 1,646,060 | 1,040,500 |
| Less: provision for impairment of receivables | (659,514) | (567,073) |
| Trade receivables and accrued revenue – net | 5,024,492 | 4,172,854 |
Movements in the provision for impairment of trade receivables are as follows:
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| At the beginning of the period/year | 567,073 | 422,544 |
| Charge for the period/year (refer note 29) | 92,441 | 144,529 |
| At the end of the period/year | 659,514 | 567,073 |
The carrying amount of the Group's trade receivables is primarily denominated in AED and approximates its fair value. Charge of credit impairment on trade receivables is mainly due to changes in gross receivables balance. There have been no changes to ECL model assumptions.
25
Page 28
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued)
for the nine-month period ended 30 September 2023 (unaudited)
16 Short-term deposits
| 30 September | 31 December | |
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Term deposits with banks | 5,627,925 | 7,532,503 |
Term deposits carry an interest ranging from 1.5% to 5.72% per annum (31 December 2022: AED 1.5% to 4.7% per annum).
Term deposits up to AED 2.4 billion (31 December 2022: AED 1.9 billion) have been kept as lien against borrowings by one of the subsidiaries.
17 Cash and cash equivalents
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Current and call accounts and short-term deposits | 5,269,847 | 5,286,848 |
| Cash on hand | 1,111 | 567 |
| 5,270,958 | 5,287,415 |
Cash and cash equivalents include AED 1,624 million (31 December 2022: AED 1,660 million) in foreign currencies. The majority of these balances are denominated in US Dollar. These balances are held for settlement of existing and anticipated liabilities denominated in foreign currencies.
Cash and cash equivalents also include AED 2,263 million (31 December 2022: AED 801 million) of cash collected by local banks and government collection agencies for and on behalf of the Group.
17.1 Cash and cash equivalents for the purpose of cash flows
For the purpose of the condensed consolidated interim statement of cash flows, cash and cash equivalents comprise the following:
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Cash and cash equivalents | 5,270,958 | 5,287,415 |
| Bank overdrafts (refer note 19) | (604,843) | (565,119) |
| Cash and cash equivalents for the purpose of cash flows | 4,666,115 | 4,722,296 |
26
Page 29
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
18 Equity
(a) Share capital
In the previous year, an amount of AED 500 million had been transferred to share capital account from Government of Dubai account. The Board of Directors of the Authority had authorised the breakup of the share capital into 50 billion shares of AED 0.01 each. All shares of the Authority shall be ranked equally with one another in all aspects. Hence, the share capital of Authority consists of authorised and paid-up capital of AED 500 million as of 30 September 2023.
(b) Capital contribution
This account represents amounts contributed by the Government of Dubai (both in kind and cash) as an Owner of the Group since the incorporation of the Group.
(c) Statutory reserve
As required by applicable law and Articles of Association of the Authority and certain subsidiaries, 5% of the net profit for each period has been transferred to a statutory reserve. Such transfers to reserves may cease when the statutory reserve equals to half of the share capitals. The reserve is not available for distribution except as stipulated by the law. The statutory reserve of the Authority has already reached the 50% threshold and hence no further transfers were made to statutory reserves. On 10 October 2022, the suspension of transfer to statutory reserve was approved by the General Assembly.
(d) Hedging reserve
The hedging reserve primarily represents the fair value of derivatives which are part of effective cash flow hedging relationships at period/year end. As the derivatives are held for hedging purposes as defined by IFRS 9, their fair value movements are retained in other comprehensive income instead of being charged to profit or loss during the period. The fair value movements will be adjusted in other comprehensive income in the same period as the corresponding hedged transaction.
(e) General reserve
In the prior years, the general reserve represented surplus distributable profits earned by the Group. In the year 2022, the balance in general reserve had been transferred to retained earnings.
19 Borrowings
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Non-current | ||
| Others (i) | 29,587,665 | 29,042,475 |
| Term loan (ii) | - | 8,275,500 |
| 29,587,665 | 37,317,975 | |
| Current | ||
| Bank overdrafts (refer note 17) | 604,843 | 565,119 |
| Others (i) | 3,463,429 | 2,806,735 |
| Term loan (ii) | 5,890,026 | - |
| 9,958,298 | 3,371,854 | |
| 39,545,963 | 40,689,829 |
27
Page 30
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
19 Borrowings (continued)
Borrowings are denominated in the following currencies:
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| US Dollars | 26,179,884 | 25,432,234 |
| UAE Dirham | 13,366,079 | 15,257,595 |
| 39,545,963 | 40,689,829 |
The borrowing balance is net of deferred borrowing cost amounting to AED 678 million (31 December 2022: AED 722 million).
The Group has secured borrowings amounting to AED 28,559 million (31 December 2022: AED 27,360 million) and unsecured borrowings amounting to AED 10,987 million (31 December 2022: AED 13,330 million).
Borrowings are secured by pledge of assets (refer note 6), corporate guarantees, government guarantees and letter of undertakings.
(i) Others
Other loan represents loans taken by subsidiary companies from various commercial banks and shareholders.
The fair values of other loans are not materially different to their carrying amounts since the interest payable on these borrowings is close to current market rates.
(ii) Term loan
During the previous year, the Authority had obtained a long-term Shariah compliant loan of AED 10,000 million from a commercial bank. The loan carried profit rate at 1-month EIBOR + margin. The term of the loan is five years and repayable in full upon its maturity.
During the current period, the Company renegotiated the loan terms with the bank and has amended the original loan agreement, whereby, the repayment term and commercial rate on loan have been revised. The revision in repayment terms has resulted in the loan being reclassified from non-current liabilities to current liabilities and in return the Company has negotiated better profit rate. Further, during the current period, the Company has prepaid AED 2,400 million (31 December 2022: AED 1,700 million) of the loan.
As of 30 September 2023, the Group was compliant with financial covenant.
The Group takes proactive measures to ensure, as far as possible, that it will always have sufficient liquidity to meet its financial obligations. The Group has positive operating cash flows amounting to AED 9,848 million for the period ended 30 September 2023, cash and cash equivalents of AED 5,271 million and undrawn facilities of AED 2,500 million as at 30 September 2023 to finance the Group's operations and mitigate the effects of fluctuations in cash flows. The Group monitors the sufficiency of funds using cash flow budgeting in which it considers the cash outflows (including impact of capital commitments), the funds that would be generated from the operations and other available sources of funding.
28
Page 31
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
20 Retirement benefit obligations
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Provision for employees' end of service benefits (refer note 20.1) | 969,079 | 948,333 |
| Provision for pensions (refer note 20.2) | 69,033 | 74,088 |
| 1,038,112 | 1,022,421 | |
| Less: non-current portion | (1,027,600) | (1,010,493) |
| Current portion (refer note 23) | 10,512 | 11,928 |
20.1 Provision for employees' end of service benefits
Movements in the provision for the employees' end of service benefits are analysed below:
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| At the beginning of the period/year | 948,333 | 937,561 |
| Charge for the period/year (refer note 31) | 67,858 | 132,870 |
| Re-measurements | (11,257) | (70,468) |
| Payments made during the period/year | (35,855) | (51,630) |
| At the end of the period/year | 969,079 | 948,333 |
20.2 Provision for pensions
20.2.1 Provision for pensions (for eligible UAE National employees who retired before 1 January 2003)
The movements in the provision for pensions are analysed below:
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| At the beginning of the period/year | 62,160 | 71,343 |
| Reversal during the period/year | - | (4,270) |
| Payments made during the period/year | (3,639) | (4,913) |
| At the end of the period/year | 58,521 | 62,160 |
29
Page 32
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
20 Retirement benefit obligations (continued)
20.2.2 Provision for pensions (for eligible UAE National employees from 1 January 2003)
Effective 1 January 2003, the Group joined a defined contribution plan operated by the Federal Pension General and Social Security Authority for its active eligible UAE National employees in accordance with the provision of Federal Law No. 7 of 1999 relating to Pension and Social Security Law. The movements in the provision for pensions are analysed below:
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| At the beginning of the period/year | 11,928 | 11,674 |
| Charge for the period/year (refer note 31) | 93,853 | 118,122 |
| Payments made during the period/year | (95,269) | (117,868) |
| At the end of the period/year | 10,512 | 11,928 |
Total provision for pension has been presented as follow:
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| At the beginning of the period/year | 74,088 | 83,017 |
| Charge for the period/year (refer note 31) | 93,853 | 118,122 |
| Reversal during the period/year | - | (4,270) |
| Payments made during the period/year | (98,908) | (122,781) |
| At the end of the period/year | 69,033 | 74,088 |
21 Lease liabilities
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| At the beginning of the period/year | 36,412 | 14,952 |
| Addition during the period/year | 2,288 | 46,930 |
| Modification | - | (13,019) |
| Payments made during the period/year | (10,700) | (12,451) |
| At the end of the period/year | 28,000 | 36,412 |
| Less: non-current portion | (16,352) | (23,528) |
| Current portion | 11,648 | 12,884 |
30
Page 33
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
22 Other long-term liabilities
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Deferred revenue | 25,596,101 | 24,940,693 |
| Advance for new connections | 6,371,187 | 6,873,698 |
| Retentions payable | 840,490 | 806,220 |
| Asset retirement obligations | 261,845 | 181,917 |
| 33,069,623 | 32,802,528 |
23 Trade and other payables
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| Consumers' security deposits | 4,600,450 | 4,231,833 |
| Trade payables | 2,126,269 | 1,214,643 |
| Capital projects payables | 2,306,525 | 2,009,818 |
| Deferred revenue | 1,451,299 | 1,374,793 |
| Retentions payable | 1,109,159 | 1,349,502 |
| Advances for new connections | 335,326 | 361,774 |
| Accrual for staff benefits | 234,556 | 278,592 |
| Retirement benefit obligations (refer note 20) | 10,512 | 11,928 |
| Dividend payables | 3,287,000 | - |
| Other payables | 2,376,645 | 2,857,760 |
| 17,837,741 | 13,690,643 |
24 Regulatory deferral account
The prices that can be charged to customers for electricity and water by the Group are subject to oversight and/or approval by the Dubai Supreme Council of Energy. Hence, the Group is subject to rate regulation. The Dubai Supreme Council of Energy through its notification issued in 2010 had allowed the Group to recover the additional costs it incurs due to the escalation in fuel prices considering 2010 as the base year from its customers.
The Dubai Supreme Council of Energy is also controlled by the Government of Dubai, and it is a related party of the Group.
On the transition date, the Group had elected to apply the requirements of IFRS 14 Regulatory Deferral Accounts and will continue to apply its current accounting policy for recognition, measurement and derecognition of this regulatory deferral account balance.
31
Page 34
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
24 Regulatory deferral account (continued)
The movement in regulatory deferral account credit balance has been detailed below:
| 30 September | 31 December | |
|---|---|---|
| 2023 | 2022 | |
| AED'000 | AED'000 | |
| (Unaudited) | (Audited) | |
| At the beginning of the period/year | 95,343 | 379,024 |
| Short collection during the period/year | (20,227) | (283,681) |
| At the end of the period/year | 75,116 | 95,343 |
25 Related party transactions and balances
The Group transacts with the Government of Dubai, subsidiaries, joint ventures and entities controlled, jointly controlled or significantly influenced by the Government of Dubai within the scope of its ordinary business activities. Since the Group is majority owned by the Government of Dubai post its listing of shares on Dubai Financial Market (DFM), these entities are jointly referred to as 'government related entities'.
The Group applies the exemption relating to government related entities under IAS 24 'Related Parties' and only discloses transactions and balances with government related entities which are individually or collectively significant. To determine significance, the Group considers various qualitative and quantitative factors including whether transactions with related parties are based on approved terms and conditions by management.
Key management personnel and entities controlled by them are also related to the Group. Key management personnel of the Group comprise the directors and executive vice presidents (EVPs) of the Authority and employees of the Authority who are acting as directors of the subsidiaries.
Related party transactions
The material transactions and balances with related parties are disclosed below, except as disclosed in notes 6, 13, 15, 19, 21, 24, 26, 27, 28, 30, 31 and 34 in this condensed consolidated interim financial information.
Sale of electricity and water and other revenues
As is common with many other entities, the Group deals with various government entities in Dubai. Quantities of electricity and water sold to UAE nationals are at subsidised rates. The Group calculates the value of these quantities supplied at approved rates and these amounts are settled by the Department of Finance (DoF), Government of Dubai.
During the current period, the Group has collected AED 57 million (for the nine-month period ended 30 September 2022: AED 50 million) in respect of handling charges (refer note 26).
Purchase of goods and services
The Group purchases fuel from entities owned by the Government of Dubai. During the current period, the Group purchased fuel amounting to AED 5,733 million (for the nine-month period ended 30 September 2022: AED 5,671 million) from various entities.
During the current period, the Group purchased water amounting to AED 7 million (for the nine-month period ended 30 September 2022: AED 5 million) from a related party of the Group.
32
Page 35
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
25 Related party transactions and balances (continued)
Transactions with banks owned by Government of Dubai
The Group transacts with various banks and financial institutions which are wholly or partially controlled by the Government of Dubai. All of the Group's transactions with such banks are on approved commercial terms. A portion of the cash and cash equivalents as disclosed in note 17 was included in deposit held with such banks.
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| Compensation to key management personnel | 2023 | 2022 | 2023 | 2022 |
| AED'000 | AED'000 | AED'000 | AED'000 | |
| (Unaudited) | (Unaudited) | (Unaudited) | (Unaudited) | |
| Salaries and short-term benefits | 86,525 | 67,513 | 15,387 | 12,801 |
| Post-employment benefits and long term benefits | 1,785 | 1,890 | 614 | 630 |
| 88,310 | 69,403 | 16,001 | 13,431 |
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
| Key management remuneration | 2023 | 2022 | 2023 | 2022 |
|---|---|---|---|---|
| AED'000 | AED'000 | AED'000 | AED'000 | |
| (Unaudited) | (Unaudited) | (Unaudited) | (Unaudited) | |
| Board of directors' remuneration | 29,625 | 29,625 | 9,875 | 9,875 |
Board members' interests
Other than remuneration paid to key management personnel, the Board members of the Authority had no beneficial interest in DEWA or its subsidiaries during period ended 30 September 2023 and 2022.
26 Revenue
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| 2023 | 2022 | 2023 | 2022 | |
| AED'000 | AED'000 | AED'000 | AED'000 | |
| (Unaudited) | (Unaudited) | (Unaudited) | (Unaudited) | |
| Sale of electricity | 14,300,940 | 13,216,926 | 6,401,029 | 5,745,905 |
| Sale of water | 4,068,582 | 3,917,449 | 1,458,898 | 1,402,325 |
| District cooling charges | 2,252,499 | 2,064,801 | 1,043,434 | 911,703 |
| Others | 1,538,774 | 1,429,994 | 518,925 | 492,292 |
| 22,160,795 | 20,629,170 | 9,422,286 | 8,552,225 |
33
Page 36
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
26 Revenue (continued)
The Group’s operations and main revenue streams are those described in the annual consolidated financial statements for the year ended 31 December 2022. The Group’s revenue is derived from contracts with customers, except for handling fees and amortisation of deferred revenue presented under ‘Others’.
Others include:
- Handling fees amounting to AED 57 million (for the nine-month period ended 30 September 2022: AED 50 million) represents amounts paid by a related party to the Group for providing collection services (refer note 25).
- Amortisation of deferred revenue amounted to AED 810 million (for the nine-month period ended 30 September 2022: AED 772 million).
26.1 Disaggregation of revenue
| For the nine-month period ended 30 September | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Electricity | Water | District cooling charges | Others | Total | ||||||
| Timing of revenue recognition | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) |
| Products and services transferred | ||||||||||
| -at a point in time | 14,300,940 | 13,216,926 | 4,068,582 | 3,917,449 | 2,252,499 | 2,064,801 | 728,484 | 658,404 | 21,350,505 | 19,857,580 |
| -over time | - | - | - | - | - | - | 810,290 | 771,590 | 810,290 | 771,590 |
| 14,300,940 | 13,216,926 | 4,068,582 | 3,917,449 | 2,252,499 | 2,064,801 | 1,538,774 | 1,429,994 | 22,160,795 | 20,629,170 |
| For the three-month period ended 30 September | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Electricity | Water | District cooling charges | Others | Total | ||||||
| Timing of revenue recognition | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) |
| Products and services transferred | ||||||||||
| -at a point in time | 6,401,029 | 5,745,905 | 1,458,898 | 1,402,325 | 1,043,434 | 911,703 | 241,160 | 218,635 | 9,144,521 | 8,278,568 |
| -over time | - | - | - | - | - | - | 277,765 | 273,657 | 277,765 | 273,657 |
| 6,401,029 | 5,745,905 | 1,458,898 | 1,402,325 | 1,043,434 | 911,703 | 518,925 | 492,292 | 9,422,286 | 8,552,225 |
27 Cost of sales
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | |
| Generation, desalination and other direct expenditure (refer note 27.1) | 9,071,933 | 8,522,832 | 3,337,385 | 3,300,207 |
| Transmission and distribution expenditure (refer note 27.2) | 3,603,157 | 3,425,941 | 1,215,634 | 1,164,861 |
| Purchase of gas, power and water | 639,994 | 635,967 | 379,838 | 302,416 |
| 13,315,084 | 12,584,740 | 4,932,857 | 4,767,484 |
34
Page 37
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
27 Cost of sales (continued)
27.1 Generation, desalination and other direct expenditure
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | |
| Fuel costs | 5,195,855 | 5,152,943 | 2,104,724 | 2,077,889 |
| Depreciation (refer note 6) | 1,874,112 | 1,654,360 | 643,770 | 551,384 |
| Employee benefit expenses (refer note 31) | 428,278 | 411,218 | 102,818 | 139,366 |
| Repairs and maintenance | 357,254 | 362,369 | 109,764 | 131,008 |
| Amortisation (refer note 7) | 9,117 | 9,117 | 3,039 | 3,039 |
| Others | 1,207,317 | 932,825 | 373,270 | 397,521 |
| 9,071,933 | 8,522,832 | 3,337,385 | 3,300,207 |
27.2 Transmission and distribution expenditure
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | |
| Depreciation (refer note 6) | 2,209,963 | 2,114,637 | 752,823 | 727,228 |
| Employee benefit expenses (refer note 31) | 1,181,753 | 1,099,266 | 392,307 | 386,392 |
| Repairs and maintenance | 162,835 | 156,683 | 55,002 | 29,110 |
| Others | 48,606 | 55,355 | 15,502 | 22,131 |
| 3,603,157 | 3,425,941 | 1,215,634 | 1,164,861 |
28 Administrative expenses
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | |
| Employee benefit expenses (refer note 31) | 1,269,401 | 1,177,184 | 445,505 | 401,284 |
| Repairs and maintenance | 227,093 | 180,728 | 101,177 | 22,827 |
| Depreciation (refer note 6) | 206,301 | 224,099 | 67,778 | 80,963 |
| Amortisation (refer note 7) | 49,262 | 51,907 | 17,310 | 17,913 |
| Insurance | 77,382 | 64,167 | 26,685 | 20,074 |
| Others | 223,031 | 233,211 | 114,688 | 18,693 |
| 2,052,470 | 1,931,296 | 773,143 | 561,754 |
35
Page 38
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
29 Credit impairment losses
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
| 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | |
| Impairment of trade receivables (refer note 15) | 92,441 | 36,907 | 52,808 | 19,907 |
30 Finance (costs)/income – net
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | |
| Finance income | ||||
| Interest income on short term bank deposits | 329,980 | 131,770 | 93,570 | 49,113 |
| Cash flow hedges – reclassified to profit or loss | 291,969 | 11,490 | 116,038 | 11,490 |
| Interest income on financial assets | 3,149 | 13,927 | 1,120 | 4,676 |
| Cash flow hedges – ineffective portion of changes in fair value of derivative financial instruments | 5,169 | 209,963 | - | 9,135 |
| Amortization of financial liabilities | 29,915 | - | 8,923 | - |
| 660,182 | 367,150 | 219,651 | 74,414 | |
| Finance costs | ||||
| Interest on bank and other borrowings | (1,817,209) | (1,081,228) | (625,980) | (401,606) |
| Cash flow hedges – reclassified to profit or loss | - | (168,412) | - | - |
| Amortization of arrangement fees | (19,327) | - | (5,064) | - |
| Cash flow hedges – ineffective portion of changes in fair value of derivative financial instruments | (121) | (194,140) | - | - |
| Interest on lease liabilities | (92) | (1,422) | (22) | (1,131) |
| (1,836,749) | (1,445,202) | (631,066) | (402,737) | |
| Amounts capitalised (refer note 6) | 432,996 | 738,507 | 138,479 | 188,073 |
| (1,403,753) | (706,695) | (492,587) | (214,664) | |
| Finance costs – net | (743,571) | (339,545) | (272,936) | (140,250) |
36
Page 39
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
31 Employee benefit expenses
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | |
| Salaries | 1,962,827 | 1,867,473 | 649,077 | 643,116 |
| Bonus | 285,194 | 167,764 | 68,668 | 55,746 |
| Retirement benefit obligations (refer note 20) | 161,711 | 167,487 | 55,615 | 65,501 |
| Other benefits | 469,700 | 484,944 | 167,270 | 162,679 |
| 2,879,432 | 2,687,668 | 940,630 | 927,042 |
32 Acquisition of DXB CoolCo FZCO (DXB Cool)
On 18 May 2023, EMPOWER entered into a sale and purchase agreement with Dubai Aviation City Corporation (DACC) to acquire 85% share capital of DXB Cool for a consideration of AED 892.5 million.
DXB Cool is a company incorporated in Dubai Airport Freezone Authority (“DAFZA”), Dubai, UAE. (License No. 5007) and has a concession agreement with DACC which grants it the sole and exclusive rights to operate, maintain and perform the district cooling services within Dubai International Airport for a term of 35 years from the commencement date (i.e. 5 July 2023).
Management performed a detailed analysis of the acquisition and determined that:
- At the acquisition date, DXB Cool does not meet the definition of business as defined in IFRS 3 and as such the transaction should be accounted for as an asset acquisition.
- The acquired asset which is a financial asset should be measured at fair value on initial recognition and subsequently at amortised cost (refer note 13).
At the reporting date, EMPOWER has recognised a financial asset (refer note 13) and a non-controlling interest amounting to AED 157.5 million.
37
Page 40
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
33 Cash generated from operating activities
| Notes | For the nine-month period ended 30 September | ||
|---|---|---|---|
| 2023 AED'000 (Unaudited) | 2022 AED'000 (Unaudited) | ||
| Operating activities | |||
| Profit for the period | 6,130,041 | 6,473,710 | |
| Adjustments for: | |||
| Depreciation | 6 | 4,290,376 | 3,993,096 |
| Amortisation | 7 | 58,379 | 61,024 |
| Provision for slow moving and obsolete inventory | 14 | 8,014 | 13,800 |
| Fair value adjustments – asset retirement obligations | 32,635 | 77,791 | |
| Charge for impairment of trade receivables | 29 | 92,441 | 36,907 |
| Deferred income | (810,290) | (771,590) | |
| Retirement benefit obligations – gratuity | 20.1 | 67,858 | 80,111 |
| Retirement benefit obligations – pensions | 20.2 | 93,853 | 87,376 |
| Ineffective portion of gain on derivative financial instruments (net) | 30 | (5,048) | (15,823) |
| Gain on sale of property, plant and equipment | (532) | (196) | |
| Finance income | 30 | (655,013) | (157,187) |
| Finance costs | 30 | 1,403,632 | 512,555 |
| Operating cash flows before changes in operating assets and liabilities | 10,706,346 | 10,391,574 | |
| Changes in operating assets and liabilities: | |||
| Inventories | 22,680 | (6,940) | |
| Trade receivables | (905,597) | (2,858,319) | |
| Other financial assets | 13 | (1,142,498) | (93,040) |
| Other assets | 12 | (237,396) | (138,410) |
| Trade and other payables | 1,559,667 | 2,325,278 | |
| Movement in regulatory deferral account credit balance | 24 | (20,227) | (396,457) |
| Net operating cash flows | 9,982,975 | 9,223,686 | |
| Payment for retirement benefit obligations – gratuity | 20.1 | (35,855) | (38,752) |
| Payment for retirement benefit obligations – pensions | 20.2 | (98,908) | (90,625) |
| Net cash generated from operating activities | 9,848,212 | 9,094,309 |
38
Page 41
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued) for the nine-month period ended 30 September 2023 (unaudited)
34 Commitments
| 30 September | 31 December | |
| 2023 | 2022 | |
| AED’000 | AED’000 | |
| (Unaudited) | (Audited) | |
| Future commitments including capital expenditures | 10,146,255 | 11,106,413 |
35 Dividend
The Authority declared a dividend of AED 6,200 million during the period ended 30 September 2023 (30 September 2022: AED 10,000 million) and a special onetime dividend of AED 1,670 million (30 September 2022: Nil).
During the current period, EMPOWER declared a dividend of AED 850 million (30 September 2022: AED 3,400 million) which includes an amount of AED 374 million (30 September 2022: AED 1,020 million) for non-controlling interest as dividend.
In addition to above, Shuaa Energy 1 P.S.C declared a dividend of AED 4.2 million (30 September 2022: AED 7.6 million). An amount of AED 2 million (30 September 2022: AED 3.7 million) was paid to the non-controlling interest as dividend.
36 Earnings per share
Basic earnings per share amounts are calculated by dividing net profit or loss for the period attributable to the Owners of the Company by the weighted average number of ordinary shares outstanding during the period.
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
| 2023 | 2022 | 2023 | 2022 | |
| AED’000 | AED’000 | AED’000 | AED’000 | |
| (Unaudited) | (Unaudited) | (Unaudited) | (Unaudited) | |
| Earnings | ||||
|---|---|---|---|---|
| Profit for the period, attributable to the Owners of the Company | 5,999,059 | 6,236,990 | 3,325,045 | 3,088,054 |
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| 2023 | 2022 | 2023 | 2022 | |
| (Unaudited) | (Unaudited) | (Unaudited) | (Unaudited) | |
| Number of shares in thousand | ||||
| Number of ordinary shares for basic earnings per share | 50,000,000 | 50,000,000 | 50,000,000 | 50,000,000 |
| For the nine-month period ended 30 September | For the three-month period ended 30 September | |||
|---|---|---|---|---|
| 2023 | 2022 | 2023 | 2022 | |
| (Unaudited) | (Unaudited) | (Unaudited) | (Unaudited) | |
| Earnings per share | ||||
| Basic earnings per share (AED) | 0.120 | 0.125 | 0.067 | 0.062 |
39
Page 42
Dubai Electricity and Water Authority (PJSC) and its subsidiaries
Notes to the condensed consolidated interim financial information (continued)
for the nine-month period ended 30 September 2023 (unaudited)
37 Comparative figures
The previous period/year figures have been regrouped wherever necessary, in order to conform to the current period presentation. The regrouping does not affect the previously reported net assets, total equity and the profit or loss and other comprehensive income.
38 UAE Corporate Tax Law
On 9 December 2022, the UAE Ministry of Finance released the Federal Decree-Law No. 47 of 2022 on the Taxation of Corporations and Businesses (the Law) to enact a Federal Corporate Tax (CT) regime in the UAE. The CT regime will become effective for accounting periods beginning on or after 1 June 2023.
The Cabinet of Ministers Decision No. 1 16/2022 effective from January 2023, has confirmed the threshold of income over which the 9% tax rate would apply, and the Law is considered to be substantively enacted.
A rate of 9% will apply to taxable income exceeding AED 375,000. A rate of 0% will apply to taxable income not exceeding AED 375,000.
For the Group, current taxes shall be accounted for as appropriate in the financial statements for the period beginning 1 January 2024. In accordance with IAS 12 Income Taxes, the related deferred tax accounting impact has been considered for the interim financial period ended 30 September 2023.
Since the corporate tax was introduced only recently, this may create tax risks in UAE that are more significant than in other countries. The Group has assessed the deferred tax implications for the nine-month period ended 30 September 2023 and, after considering its interpretations of applicable tax law, official pronouncements, cabinet decisions and ministerial decisions (especially with regard to transition rules), it has been concluded that it is not expected to be material.
The Group shall continue to monitor critical Cabinet Decisions to determine the impact on the Group, from deferred tax perspective.
40