Clarification from the company regarding the accumulated losses DSI
Document3 pages, a scan, read by AshumOpen DFM’s file
Page 1
| Detailed Analysis of Accumulated Losses
Date:
26 July 2024
Name of the Listed Company:
Drake & Scull International PJSC
Define the period of the financial statements: 30 June 2024Value of the Accumulated losses ‘ AED 000’: 1,680,431Accumulated losses to paid-up capital ratio (%): 58%
The main reasons for accumulated losses and the period in which these losses began. (Determine the period in which these losses began to appear in the
company's financial statements):
The accumulated losses incurred mainly due to the
following:
1. Work in progress and contract receivables in legacy projects in GCC and India.
2. Full impairment of Goodwill and Trademark as at December 31, 2018.
8. Because of poor performance on legacy projects whereby the actual costs of completing projects were more than the budgets in addition to liquidating bonds.
4. Bank bans and court orders.
The losses began to appear in the company’s financial statements in Q3 2015 financial statements published on DFM.
Summary of the steps and initiatives undertaken
by the company to address the accumulated losses:
. Implementation of restructuring business
plan.
. Improvement of the liquidity position after
raising the new equity.
Developing effective and efficientoperational business practices.
Pursue legal cases to collect all receivables.
Controlling the overhead at the optimal level.
Page 1 of 3
Page 2
The date on which the company's general assembly
approved the plan for dealing with accumulated
losses:
The restructuring settlement plan approved by Dubai Court of Appeal on 1 November 2023.
The Measures that will be taken to deal with the accumulated losses and the approved plan
The time frame for
implementing the
The implemented action and
Reasons for not implementing
Any
modifications
Actions action according the percentage of or changes the action or delaying
to the approved implementation made to theplan actionWinning 6 months The restructuring The late completion of No
| new process was completed | the restructuring |
| profitable on 3 June 2024 andthis | process led to major |
projects action is still at the delay in unlocking the initial phase. bank accounts and
obtaining bankguarantees for newprojects.
Recovery 1 Year Started at early stage The legal status of the No of before closing the group before closing receivables restructuring process. the restructuring previously It is a continuous process was the main fully process and will be reason behind the provided enhanced and delay.
for. accelerated afterclosing therestructuring process.
| Collections | Subject to Started at early stage The previous liquidity No |
| fromlegal | local courts before closing the crunch of the group led |
cases time lines restructuring process. to major delay in
The group alreadydisclosed on DFM thestatus of some legalcases.
closing the legal cases
in favor of the company.
Page 2 of 3
Page 3
| The Name of the Authorized Signatory | Fadi Baraki |
| Designation | Chief Financial Officer |
| Signature and Date | 26 July 2024 |
Company's Seal |
Page 3 of 3