Clarification from the company regarding the accumulated losses DSI

Drake & Scull International PJSC 3 pages

Document3 pages, a scan, read by AshumOpen DFM’s file

Page 1

| Detailed Analysis of Accumulated Losses

Date:

26 July 2024

Name of the Listed Company:

Drake & Scull International PJSC

Define the period of the financial statements: 30 June 2024Value of the Accumulated losses ‘ AED 000’: 1,680,431Accumulated losses to paid-up capital ratio (%): 58%

The main reasons for accumulated losses and the period in which these losses began. (Determine the period in which these losses began to appear in the

company's financial statements):

The accumulated losses incurred mainly due to the

following:

1. Work in progress and contract receivables in legacy projects in GCC and India.

2. Full impairment of Goodwill and Trademark as at December 31, 2018.

8. Because of poor performance on legacy projects whereby the actual costs of completing projects were more than the budgets in addition to liquidating bonds.

4. Bank bans and court orders.

The losses began to appear in the company’s financial statements in Q3 2015 financial statements published on DFM.

Summary of the steps and initiatives undertaken

by the company to address the accumulated losses:

. Implementation of restructuring business

plan.

. Improvement of the liquidity position after

raising the new equity.

Developing effective and efficientoperational business practices.

Pursue legal cases to collect all receivables.

Controlling the overhead at the optimal level.

Page 1 of 3

Page 2

The date on which the company's general assembly

approved the plan for dealing with accumulated

losses:

The restructuring settlement plan approved by Dubai Court of Appeal on 1 November 2023.

The Measures that will be taken to deal with the accumulated losses and the approved plan

The time frame for

implementing the

The implemented action and

Reasons for not implementing

Any

modifications

Actions action according the percentage of or changes the action or delaying

to the approved implementation made to theplan actionWinning 6 months The restructuring The late completion of No

new process was completedthe restructuring
profitable on 3 June 2024 andthisprocess led to major

projects action is still at the delay in unlocking the initial phase. bank accounts and

obtaining bankguarantees for newprojects.

Recovery 1 Year Started at early stage The legal status of the No of before closing the group before closing receivables restructuring process. the restructuring previously It is a continuous process was the main fully process and will be reason behind the provided enhanced and delay.

for. accelerated afterclosing therestructuring process.

CollectionsSubject to Started at early stage The previous liquidity No
fromlegallocal courts before closing the crunch of the group led

cases time lines restructuring process. to major delay in

The group alreadydisclosed on DFM thestatus of some legalcases.

closing the legal cases

in favor of the company.

Page 2 of 3

Page 3

The Name of the Authorized SignatoryFadi Baraki
DesignationChief Financial Officer
Signature and Date26 July 2024

Company's Seal |

Page 3 of 3